  280. The traditional organizational form has the disadvantage of:
  A. Complex functional budgeting
  B. Poorly established communication channels
  C. No single focal point for clients/sponsors
  D. Slow reaction capability
  E. Inflexible use of manpower
  ANS: C
  
  281. Things that distort, distract, or muddle the communication process are called:
  A. noise
  B. selective filtering
  C. selective perception
  D. medium problems
  E. All of the above.
  ANS: A
  
  282. Which is not a consideration in a make or buy decision?
  A. Cost factors (least cost alternatives)
  B. Competitors' method of sourcing
  C. Existence of sufficient administration/technical personnel
  D. Political and social factors
  E. None of the above.
  ANS: B
  
  283. A Work Breakdown Structure:
  A. assures all work is identified
  B. subdivides the project into manageable segments
  C. provides the project sponsor with a time-phase task summary
  D. both A and B
  E. All of the above.
  ANS: D
  
  284. A project manager can exchange information with the project team using which media?
  A. tactile
  B. audio
  C. olfactory
  D. visual
  E. All of the above.
  ANS: E
  
  285. During project execution, the customer authorizes and funds a scope change which requires a major change in the schedule. The baseline
  schedule:
  A. Now becomes the new schedule, including the changes, and the original baseline is disregarded.
  B. Is still the original baseline but annotated to reflect that a change has taken place.
  C. Is amended to reflect the scope change, but the original baseline is still maintained for post-project review.
  D. Is meaningless since every schedule update changes the baseline (i.e., a rubber baseline.)
  E. Is the same since baseline schedules cannot change once the development phase is completed.
  ANS: C
  
  286. Sensitivity analysis can be used in risk analysis to:
  A. Substitute for uncertainty analysis in risk quantification
  B. estimate the level of risk aversion adopted by management
  C. estimate the effect of change of one project variable on the overall project
  D. A and B
  E. All of the above.
  ANS: C
  
  287. The Pareto Principle is a technique used by quality managers to determine which quality control problems of a particular service or
  manufacturing process should be corrected. Which of the following statements represents the philosophy of the principle?
  A. In order to minimize financial losses from quality control problems, all problems which have a measurable cost associated with them should be
  corrected.
  B. the majority of defects are caused by a small percentage of the identifiable problems. Improvements efforts should be reserved for these vital
  few problems.
  C. in order to achieve zero defects, all quality control problems, including those which do not have a direct financial cost should be corrected.
  D. generally, 80 % of the quality control problems are justifiable for correction via cost-benefit analysis. The remaining 20% are not financially
  worthy of improvement efforts.
  E. A and D
  ANS: B
  
  288. The budgeted cost of the work performed (BCWP) for a task that has just been completed can be calculated by:
  A. Multiplying the actual hours worked on the project by the budgeted labor rate.
  B. Multiplying the budgeted hours to complete the task by the budgeted labor rate.
  C. Dividing the actual hours required to complete the task by the budgeted labor rate.
  D. Cannot be determined.
  E. None of the above
  ANS: B
  
  289. The project manager has, as a prime responsibility, to assure proper integration of activities. In which organizational form does the project
  manager probably have the easiest time in integrating work?
  A. Matrix
  B. Classical
  C. Expediter
  D. Coordinator
  E. Pure project
  ANS: E
  
  290. There are four methods of government procurement. Which is not one of these methods?
  A. Assistance
  B. Sealed bidding
  C. Competitive proposals
  D. Acquisition
  E. Small purchases
  ANS: D
  
  
[] [返回上一页] [打 印]
网络评论 (评论内容只代表网友观点,与本站立场无关!)

用户名: 查看更多评论

分 值:100分 85分 70分 55分 40分 25分 10分 0分

内 容:

         (注“”为必填内容。) 验证码: 验证码,看不清楚?请点击刷新验证码

本类热门文章
相关文章
关于本站 - 网站帮助 - 广告合作 - 下载声明 - 友情连接 - 网站地图 -