  451. In general, groups will ____ the average individual problem solver on problems with multiple stages.
  A. Perform better than
  B. Perform worse than
  C. Take less time than
  D. Do about as well as
  E.
  ANS: A
  
  452. The scope baseline/project charter is prepared by the:
  A. Project manager
  B. Project manager and project office
  C. Project manager, project office and functional team
  D. Project manager, project office, functional team and project sponsor
  E. Project manager, project sponsor and customer/user
  ANS: E
  
  453. Warranty cost is an example of an _____ .
  A. internal failure cost
  B. appraisal cost
  C. external failure cost
  D. customer satisfaction cost
  E. All of the above.
  ANS: C
  
  454. Which of the following does not contribute to increased Schedule Risk?
  A. labor shortage
  B. contractor claims
  C. lack of access
  D. sponsor scope changes
  E. all may increase schedule risk
  ANS: E
  
  455. Which of the following is considered a method of accelerated depreciation:
  A. sum-of-the-years digit
  B. straight-line
  C. double-declining-balance
  D. A and C
  E. All of the above.
  ANS: D
  
  456. Cost management includes processes that are required to maintain financial control of projects. These processes may include:
  A. economic evaluation
  B. cost estimating
  C. cost forecasting
  D. B and C
  E. All of the above.
  ANS: E
  
  457. In crashing a task, you would focus on:
  A. As many tasks as possible.
  B. Non critical tasks.
  C. Accelerating performance of tasks on critical path.
  D. Accelerate performance by minimizing cost.
  E. A and D.
  ANS: C
  
  458. Inspection processes are considered _____.
  A. an investment in the future
  B. an effective corrective process
  C. a necessary control process
  D. insults to production line employees
  E. None of the above.
  ANS: C
  
  459. Standard deviation of project completion is _____ .
  A. a relationship of the uncertainty of critical path activities.
  B. an indicator of project end date target confidence
  C. a function of critical path, leveling and project costs.
  D. A and B
  E. All of the above.
  ANS: D
  
  460. The project team form of organization confers both advantages and disadvantages. Disadvantages of the project form include:
  A. Conflict in authority between project manager and functional managers
  B. Dual allegiance on part of team members
  C. Complex prioritization of resources
  D. Loss of developed procedures on project dissolution
  E. All of the above
  ANS: E
  
[] [返回上一页] [打 印]
网络评论 (评论内容只代表网友观点,与本站立场无关!)

用户名: 查看更多评论

分 值:100分 85分 70分 55分 40分 25分 10分 0分

内 容:

         (注“”为必填内容。) 验证码: 验证码,看不清楚?请点击刷新验证码

本类热门文章
相关文章
关于本站 - 网站帮助 - 广告合作 - 下载声明 - 友情连接 - 网站地图 -